Larchmont Train Station Project Back on Track?
by Judy Silberstein
(June 5, 2003) It’s starting to
look like Larchmont’s
stalled train station renovation may be back on track, the
Gazette learned this week.
“We are looking at rebidding the project this summer,
or maybe this fall,” said Metro-North Railroad spokesperson
Dan Brucker. “We expect to award the contract
later this year, after reviewing the bids, and to start construction
in early 2004.”
The on-again/off-again project is meant to construct a
new overpass and station house and to otherwise spruce up
the
station
and make it more accessible. (See: Metro-North
Unveils Latest Station Design.) It had been included
in Metro-North's 2002-2004 Capital Program
and was slated to begin in 2002. But after gaining some speed
last summer,
the project ground to a halt in the winter when construction
bids came in at unacceptable levels. (See: Larchmont
Station Renovation On-Hold)
"To the extent that we're making progress, I'm thrilled,"
said Larchmont Deputy Mayor Liz Feld. "We're all looking
forward to getting this underway as soon as possible." 
The first time around, the bids came in too high, partly
because of insurance and logistical difficulties that
may now be solved. Metro-North expects
to
have better luck reining
in insurance charges because they plan to extend protection
under existing policies and avoid the high costs of having
contractors buy their own.
The previous bid was also hamstrung because a major portion
of the work needed to be scheduled during relatively short
stretches in the middle of the night. That was the only time
available for stopping train traffic so large machinery could
be brought onto the tracks. Late-night work and short
shifts translated into very high labor costs over a long
period.
It had not been possible to schedule track access during
the day because a Larchmont closure would add to disruptions
already taking place up the line in Connecticut. By 2004,
the Connecticut project will be finished and Larchmont can
have a daytime work slot for eight months – long enough
to get the job done at a lower cost.
Deputy Mayor Feld was glad to learn that more daytime work
would be possible. "The original schedule was designed
to minimize disruption and inconvenience to the commuters
and area residents,"
she explained. "But there was some concern about night
time construction
noise and lights."
"If the work can be done during the day, we'll all be better
off," she said.
|